Here are the latest updates on construction progress at the Charleston Tech Center!

  • 07/27/2020

    Progress and then some

    CTC garage screen are almost all installed, windows mostly installed on upper floors, and some other cool pics of progress

  • 06/30/2020

    Yup...staying on schedule

    The super cool garage screens are starting to get installed and the windows  on the south side are almost done.

  • CTC exterior - north wiewCTC exterior - north wiew
    Window frame + glass installationWindow frame + glass installation
    Main HVAC distributionMain HVAC distribution
    First view of garageFirst view of garage
    Sprinkler system installationSprinkler system installation
    Future corner storeFuture corner store
    CTC exterior - northCTC exterior - north
    window frame installation - southwindow frame installation - south
    CTC exterior - Morrison Drive (east) viewCTC exterior - Morrison Drive (east) view

    06/04/2020

    All Hands on Deck

    Development of the CTC keeps rolling - progress is being made on window frames and glass, supply ducts for the Heat and Air system, garage is rolling, sprinklers being installed and more.

  • 04/15/2020

    Panels Get Installed On CTC's Steel Frame

    Progress on the CTC continues with the building panels being installed on the steel frame. Construction on the building and the garage remains on schedule for a year end delivery.

  • 03/16/2020

    Progress Amidst The Chaos

    The steel beams on the CTC get their fire retardant foam while the parking garage entrance emerges.

  • "Last Beam"day
    Perseverance pays offPerseverance pays off
    Steel workers sign the beamSteel workers sign the beam
    Last beam almost in placeLast beam almost in place
    Last beam in placeLast beam in place
    Adjacent 815 space parking garage Adjacent 815 space parking garage

    01/31/2020

    Last Beam Ceremony

    Another milestone for the Charleston Tech Center with the installation of the last steel beam. Watch video here >

  • 01/07/2020

    Lucky Seven?

    Randomly driving by the CTC site and witnessed something epic - the first panel and the first column for the CTC Garage. Yes, an office building with 812 parking spaces thanks to the CTC partnership with the City of Charleston. Watch video here >

  • 12/30/2019

    Framing - Four down and two to go

    Progress continues on the Charleston Tech Center with the fifth and sixth floors remaining to be framed.

  • 11/11/2019

    Going Vertical!

    Construction at the Charleston Tech Center rolls forward. Today marks the start of steel beams being installed. While this is happening, the foundation for the 812 space parking garage is forming.

  • Pole relocation - beforePole relocation - before
    Pole relocation - duringPole relocation - during
    Pole relocation - afterPole relocation - after

    08/20/2019

    Electrical pole relocation

    Dominion Energy completed the necessary relocation of the construction site's main power pole today.

  • GroundbreakingGroundbreaking
    Steve Dykes, Bob Hitt & Ernest AndradeSteve Dykes, Bob Hitt & Ernest Andrade
    Joseph P. Riley, Jr. (former Mayor) addresses the gatheringJoseph P. Riley, Jr. (former Mayor) addresses the gathering
    SC Commerce Secretary, Bobby HittSC Commerce Secretary, Bobby Hitt

    07/16/2019

    Groundbreaking ceremony

    Iron Bridge Capital Partners, LLC and the Charleston Digital Corridor are pleased to announce the commencement of construction of the Charleston Tech Center (CTC), an architecturally modern, six-floor office building located in Downtown Charleston. The CTC is targeted to start-up, early-stage and mature tech companies. The development of the CTC, a 92,000 square foot building is scheduled for completion in late 2020, includes an adjacent 812 space parking garage that will be owned and operated by the City of Charleston. More event pics here.