CTC Timelapse & Updates
Charleston Tech Center timelapse video.
Latest Updates
Here are the latest updates on construction progress at the Charleston Tech Center!
-
10/30/2020
Work continues with the finish line in view
The parking garage is almost complete as access controls get installed. Landscaping is going in and the stage at the park is almost there.
-
09/30/2020
Getting closer to the finish line
Work continues of the CTC and the accompanying garage. Floor buildout begin! Thanks to the building quality and architecture and safety features including UV/Merv15 ventilation, leasing activity is strong.
-
08/31/2020
More finishing touches
Building window and curtain wall glass mostly installed; park pavers get rolling; CTC parking garage perforated skin installation complete.
-
07/27/2020
Progress and then some
CTC garage screen are almost all installed, windows mostly installed on upper floors, and some other cool pics of progress
-
06/30/2020
Yup...staying on schedule
The super cool garage screens are starting to get installed and the windows on the south side are almost done.
-
06/04/2020
All Hands on Deck
Development of the CTC keeps rolling - progress is being made on window frames and glass, supply ducts for the Heat and Air system, garage is rolling, sprinklers being installed and more.
-
04/15/2020
Panels Get Installed On CTC's Steel Frame
Progress on the CTC continues with the building panels being installed on the steel frame. Construction on the building and the garage remains on schedule for a year end delivery.
-
03/16/2020
Progress Amidst The Chaos
The steel beams on the CTC get their fire retardant foam while the parking garage entrance emerges.
-
01/31/2020
Last Beam Ceremony
Another milestone for the Charleston Tech Center with the installation of the last steel beam. Watch video here >
-
01/07/2020
Lucky Seven?
Randomly driving by the CTC site and witnessed something epic - the first panel and the first column for the CTC Garage. Yes, an office building with 812 parking spaces thanks to the CTC partnership with the City of Charleston. Watch video here >
-
12/30/2019
Framing - Four down and two to go
Progress continues on the Charleston Tech Center with the fifth and sixth floors remaining to be framed.
-
11/11/2019
Going Vertical!
Construction at the Charleston Tech Center rolls forward. Today marks the start of steel beams being installed. While this is happening, the foundation for the 812 space parking garage is forming.
-
08/20/2019
Electrical pole relocation
Dominion Energy completed the necessary relocation of the construction site's main power pole today.
-
07/16/2019
Groundbreaking ceremony
Iron Bridge Capital Partners, LLC and the Charleston Digital Corridor are pleased to announce the commencement of construction of the Charleston Tech Center (CTC), an architecturally modern, six-floor office building located in Downtown Charleston. The CTC is targeted to start-up, early-stage and mature tech companies. The development of the CTC, a 92,000 square foot building is scheduled for completion in late 2020, includes an adjacent 812 space parking garage that will be owned and operated by the City of Charleston. More event pics here.